April, 2025

Phase 3 Caisson and Rubble Works for the Reinforcement of the Ulsan All-Around Breakwater Revetment [울산 전사방파호안 보강공사 3단계 케이슨 및 사석공]

Caisson Fabrication & Installlation 1ea (6,000Ton), Crushed stone 24,271m3, Armor Stone 5,869m3, Con’c Block Fabrication & installation 233ea (5~70ton)
October, 2024

Construction of earthworks and Temporary earth retaining wall of the new office building in Hanam, Sungwon Adpia [성원애드피아 하남 신사옥 신축공사 중 토공 및 흙막이 공사]

On-site earth works (incl. Ballast works) 141,304m3, C.I.P 7,437m, Drainage work(ADG) 1LS, PRD 1,808m [Full Top/Down Method]
September, 2023

Civil and Structural Works, Package 2, Dangjin LNG Terminal Phase 1 Permanent Facilities Construction Project, Korea Gas Corporation (Dangjin Base) [당진 가스공사 당진기지 1단계 본설비 건설공사 중 토목 구조물공사 PKG2]

Pile head reinforcement, Concrete construction (Pump station, Discharge box, Discharge Pond), Under wall excavation