Construction of General Industrial Complex Site in Yangchon/Yongjeong District Zone 3, for earthworks and underwater construction [양촌 용정지구 일반산업단지 부지조성공사 토공 및 수중공사 3공구]

Location & Map

 

Photos

  • Project Name : Construction of General Industrial Complex Site in Yangchon/Yongjeong District Zone 3, for earthworks and underwater construction
  • Project Owner : SK Oceanplant / SK Ecoplant Co., Ltd.
  • Period : Jun. 2023 ~ Sep. 2026
  • Summary :

On-site Earth works 1,696,423m3, Ballasting works 1,305,044m3, PC Box fabrication & installation 2,088m, Soil nail & Rock bolt works 1LS