- Project Name : Phase 3 Caisson and Rubble Works for the Reinforcement of the Ulsan All-Around Breakwater Revetment
- Project Owner : Ulsan Regional Office of Oceans and Fisheries / HD Hyundai Heavy Industries Co., Ltd.
- Period : Apr. 2025 ~ Apr. 2026
- Summary :
Caisson Fabrication & Installlation 1ea (6,000Ton), Crushed stone 24,271m3, Armor Stone 5,869m3, Con’c Block Fabrication & installation 233ea (5~70ton)