  • Project name : Donghae Port Phase-III Zone-2 Underwater & Concrete structure construction Project (동해항 3단계 방파호안 축조공사 2공구 수중 및 상부공)
  • Project owner :
    Donghae regional office of oceans and fisheries / SK E&C (동해지방해양수산청 / SK건설)
  • Period : 2019.Oct ~ 2021.Oct
  • Summary :

Breakwater Z-2-2, Z-3, Z-4, Caisson installation 26EA, Breakwater upper concrete structure construction 90,000m3, Supplementary construction 1LS