Underwater, dredging and port construction during reinforcement work of Ulsan New Port Southern Breakwater (1-1) [울산신항 남방파제(1-1공구) 보강공사 중 수중, 준설 및 항만공사]

Location & Map

 

Photos

  • Project Name : Underwater, dredging and port construction during reinforcement work of Ulsan New Port Southern Breakwater (1-1)
  • Project Owner : Ulsan Regional Office of Oceans and Fisheries / Hyundai Engineering & Construction
  • Period : Oct. 2021 ~ Jul. 2025
  • Summary :

Sea Lock remove and installation : 4,163ea, Concrete block & TTP installation 4,217ea, Caisson fabrication and installation 24ea (5,000Ton), Caisson filling with slag 188,456m3, Caisson slit panel fabrication & installation 1LS, Caisson upper structure construction 1LS (Concrete 38,929m3, Rebar 604Ton)