- Project name : Dredging for Shin-Kori nuclear power plant No.1&2 (신고리 원자력 1,2호기 공사)
- Project owner : Korea Hydro & Nuclear Power(KHNP) / Hyundai E&C (한국수력원자력(주) / 현대건설(주))
- Period : 2005.FEB ~ 2009.JUN
- Summary :
Grab Dredging
Soft rock : 4,277m3
Weathered rock : 12,266m3
Sand : 276,584m3
Gravel : 42,279m3
*No location is shown due to security reasons.