April, 2025

Phase 3 Caisson and Rubble Works for the Reinforcement of the Ulsan All-Around Breakwater Revetment [울산 전사방파호안 보강공사 3단계 케이슨 및 사석공]

Caisson Fabrication & Installlation 1ea (6,000Ton), Crushed stone 24,271m3, Armor Stone 5,869m3, Con’c Block Fabrication & installation 233ea (5~70ton)
March, 2025

Busan Cheonseong Port South Breakwater Construction Project [부산 천성항 남방파제 건설공사]

Crushed stone & armor stone 25,850m3, Grading 11,589m3, Con’c Block Fabrication & installation 1,157ea, T.T.P Fabrication & Installation 2,000ea, Light House 1ea
December, 2024

Construction of the East Breakwater in Gukdo-Port [국도항 동방파제 축조공사 중 방파제 축조공사]

Crushed Stone 48,384m3, Armor Stone 4,532m3, Grading for Caisson 10,624m2, Caisson Fabrication & installation 3ea (5,000Ton)
October, 2024

Construction of earthworks and Temporary earth retaining wall of the new office building in Hanam, Sungwon Adpia [성원애드피아 하남 신사옥 신축공사 중 토공 및 흙막이 공사]

On-site earth works (incl. Ballast works) 141,304m3, C.I.P 7,437m, Drainage work(ADG) 1LS, PRD 1,808m [Full Top/Down Method]
August, 2024

Dredging Works for the LPG Berth at SK Gas Pyeongtaek Terminal [SK가스 평택기지 LPG부두 준설공사]

Grab Dredging 159,403m3, Unloading Disposal 1LS
February, 2024

Breakwater restoration work during typoon damage restoration work at Namyang Port[남양항 태풍피해 복구공사 중 방파제 복구공사]

T.T.P Installation 640ea (40~64Ton), Tripod installation 1,124ea (5Ton), Concrete work 8,741m3, Raising and Reinstalling Breakwater Block 1LS
October, 2023

Underwater construction during the construction of a dumping site for dredged soil in Gwangyang Port (1 section) [광양항 광역 준설토 투기장 조성공사 중 수중공사(1구간)]

September, 2023

Civil and Structural Works, Package 2, Dangjin LNG Terminal Phase 1 Permanent Facilities Construction Project, Korea Gas Corporation (Dangjin Base) [당진 가스공사 당진기지 1단계 본설비 건설공사 중 토목 구조물공사 PKG2]

Pile head reinforcement, Concrete construction (Pump station, Discharge box, Discharge Pond), Under wall excavation
September, 2023

Concrete construction of breakwater during construction of Ulsan New Port Southern Breakwater 2-3 [울산신항 남방파제 2-3공구 축조공사 중 방파제 구체공사]

Caisson installation 22ea (13,000Ton), Caisson Top concrete pouring 8,343m3, Caisson stuffing (Slag) 297,810m3