Home
About
Projects
Equipments
Sustainability
English
한국어
✕
Filter by
Categories
Tags
Authors
Show all
All
Caissons
Dredging
Other Works
Pile Driving
Uncategorized
All
Caisson Install
caissons
Featured
Grab Dredging
Jacket Install
Pile Driving
Pump Dredging
All
Woongjin
April, 2025
Categories
Caissons
Phase 3 Caisson and Rubble Works for the Reinforcement of the Ulsan All-Around Breakwater Revetment [울산 전사방파호안 보강공사 3단계 케이슨 및 사석공]
Caisson Fabrication & Installlation 1ea (6,000Ton), Crushed stone 24,271m3, Armor Stone 5,869m3, Con’c Block Fabrication & installation 233ea (5~70ton)
March, 2025
Categories
Uncategorized
Busan Cheonseong Port South Breakwater Construction Project [부산 천성항 남방파제 건설공사]
Crushed stone & armor stone 25,850m3, Grading 11,589m3, Con’c Block Fabrication & installation 1,157ea, T.T.P Fabrication & Installation 2,000ea, Light House 1ea
December, 2024
Categories
Caissons
Uncategorized
Construction of the East Breakwater in Gukdo-Port [국도항 동방파제 축조공사 중 방파제 축조공사]
Crushed Stone 48,384m3, Armor Stone 4,532m3, Grading for Caisson 10,624m2, Caisson Fabrication & installation 3ea (5,000Ton)
October, 2024
Categories
Other Works
Construction of earthworks and Temporary earth retaining wall of the new office building in Hanam, Sungwon Adpia [성원애드피아 하남 신사옥 신축공사 중 토공 및 흙막이 공사]
On-site earth works (incl. Ballast works) 141,304m3, C.I.P 7,437m, Drainage work(ADG) 1LS, PRD 1,808m [Full Top/Down Method]
August, 2024
Categories
Dredging
Dredging Works for the LPG Berth at SK Gas Pyeongtaek Terminal [SK가스 평택기지 LPG부두 준설공사]
Grab Dredging 159,403m3, Unloading Disposal 1LS
February, 2024
Categories
Other Works
Breakwater restoration work during typoon damage restoration work at Namyang Port[남양항 태풍피해 복구공사 중 방파제 복구공사]
T.T.P Installation 640ea (40~64Ton), Tripod installation 1,124ea (5Ton), Concrete work 8,741m3, Raising and Reinstalling Breakwater Block 1LS
October, 2023
Categories
Other Works
Underwater construction during the construction of a dumping site for dredged soil in Gwangyang Port (1 section) [광양항 광역 준설토 투기장 조성공사 중 수중공사(1구간)]
September, 2023
Categories
Uncategorized
Civil and Structural Works, Package 2, Dangjin LNG Terminal Phase 1 Permanent Facilities Construction Project, Korea Gas Corporation (Dangjin Base) [당진 가스공사 당진기지 1단계 본설비 건설공사 중 토목 구조물공사 PKG2]
Pile head reinforcement, Concrete construction (Pump station, Discharge box, Discharge Pond), Under wall excavation
September, 2023
Categories
Caissons
Concrete construction of breakwater during construction of Ulsan New Port Southern Breakwater 2-3 [울산신항 남방파제 2-3공구 축조공사 중 방파제 구체공사]
Caisson installation 22ea (13,000Ton), Caisson Top concrete pouring 8,343m3, Caisson stuffing (Slag) 297,810m3
1
2
3
...
14
Next page