August, 2012

Samcheok green power No.1,2 water breaker construction [삼척 그린파워 1,2호기 방파제 축조공사]

Project name : Samcheok green power No.1,2 water breaker construction (삼척 그린파워 1,2호기 방파제 축조공사) Project owner : KOREA Southern Power / Daewoo E&C (한국남부발전(주) / (주)대우건설) Period : 2012.AUG ~ 2015.DEC Summary : Pre-cast block installation 454EA, Crushed stone 507,481m3
July, 2012

Jeju aewol port phase-II project [제주 애월항 2단계 개발사업]

Project name : Jeju aewol port phase-II project (제주 애월항 2단계 개발사업) Project owner : Jeju city / SK E&C (제주특별자치도 / SK건설(주)) Period : 2012.JUL ~ 2015.FEB Summary : Caisson fabrication & installation 11EA
May, 2012

Dangjin hyundai steel pier construction [당진 현대제철 철재 전용부두 축조공사]

Project name : Dangjin hyundai steel pier construction (당진 현대제철 철재 전용부두 축조공사) Project owner : Hyundai steel / hyundai AMCO (현대스틸(주) / 현대엠코(주)) Period : 2012.MAY ~ 2013.FEB Summary : Caisson fabrication & installation 10EA, Crushed stone 148,452m3, Dredging 219,010m3
May, 2012

Dangjin seodang bridge and BC girder project [서당교 및 BC 구축물 공사]

Project name : Dangjin seodang bridge and BC girder project [서당교 및 BC 구축물 공사] Project owner : Hyundai steel / Hyundai AMCO (현대제철(주) / 현대엠코(주)) Period : 2012.MAY ~ 2013.MAY Summary : Pile driving 5,302m , Rigid-frame girder fabrication & installation 8EA
May, 2012

Boryeong youngbo industrial complex site construction [보령 영보 일반산업단지 조성공사]

Project name : Boryeong youngbo industrial complex site construction (보령 영보 일반산업단지 조성공사) Project owner : GS caltex / GS E&C (GS칼텍스(주) / GS건설(주)) Period : 2012.APR ~ 2019.JUL Summary : Land excavation 3,268,550m3, Embankment construction 2,176,583m3
April, 2012

Geoje A.N. inner-berthing pier dredging project [거제 A.N. 안벽 준설공사]

Project name : Geoje A.N. inner-berthing pier dredging project (거제 A.N. 안벽 준설공사) Project owner : DSMEC / Samwoong Construction (대우조선해양건설 / 삼웅건설(주)) Period : 2012.APR ~ 2013.JAN Summary : Dredging 377,037m3
April, 2012

Gumi high tech-valley complex site construction [구미 하이테크밸리 조성공사]

Project name : Gumi high tech-valley complex site construction (구미 하이테크밸리 조성공사) Project owner : K-water / Posco E&C (한국수자원공사 / (주)포스코건설) Period : 2012.APR ~ 2019.JUL Summary : Auxiliary layer paving 93,583m3, Asphalt concrete paving 373,483m2, small block paving 83,520m2, boundary stone installation 146,413m
March, 2012

Pohang southern water breaker 1-2 project [포항 남방파제 1단계 2공구 축조공사]

Project name : Pohang southern water breaker 1-2 project (포항 남방파제 1단계 2공구 축조공사) Project owner : Pohang regional office of oceans and fisheries / GS E&C (포항지방해양수산청 / GS건설(주)) Period : 2012.MAR ~ 2013.NOV Summary : Southern water breaker 500m, caisson fabrication & installation 14EA, Pre-cast block 1,094EA, Crushed […]
February, 2012

Oman Sur IPP intake & outfall project [오만 수르 발전소 해수 취수구 및 배수지 축조공사]

Project name : Oman Sur IPP intake & outfall project (오만 수르 발전소 해수 취수구 및 배수지 축조공사) Project owner : Pheonix power company SAOC / Daewoo E&C (Pheonix power company SAOC / (주)대우건설) Period : 2012.FEB ~ 2014.JUL Summary : GRP Pipe installation 3,980m, Quarry rock 285,000m3, Dreding 227,787m3, […]