Ulsan port sea route-B8 [울산항 항로곡선화 및 8부두 전면 준설공사]

Project name : Ulsan port sea route – Berth8 (울산항 항로긱선화 및 8부두 전면 준설공사) Project owner : Ministry of Maritime Affairs and Fisheries (South Korea, MOMAF) / DAEWOO (울산해양수산청 / (주)대우건설) Period : 2001.DEC ~ 2002.DEC Summary : Grab Dredging Soil : 22,318m3 Rock : 109,914m3
August, 2001

Port of Gwangyang-dredging stage2 [광양항 2단계 준설공사]

Project name : Port of Gwangyang-stage2 (광양항 2단계 준설공사) Project owner : Ministry of Maritime Affairs and Fisheries (South Korea, MOMAF) / HDC (목포해양수산청 / 현대산업개발(주)) Period : 2001.AUG ~ 2001.DEC Summary : Grab Dredging Soil : 28,700m3 Rock : 173,520m3
October, 2000

Tongyeong LNG Terminal [통영생산기지 항만시설공사]

Project name : Tongyeong LNG Terminal (통영생산기지 항만시설공사) Project owner : Korea Gas Corporation (KOGAS) / Samsung Heavy Industries (SHI) (한국가스공사 / 삼성중공업(주)) Period : 2000.FEB ~ 2001.DEC Summary : Grab Dredging Rock : 775,509m3 Jacket Installation 10.0 * 16.2 * 21.1 : 37 Jackets Jacket Pile 1,016, 914.4 : […]
May, 2000

Ulsan new port [울산 신항 방파제 공사]

Project name : Ulsan new port (울산 신항 방파제 공사) Project owner : Ministry of Maritime Affairs and Fisheries (South Korea, MOMAF) / Samsung E&C (울산해양수산청 / 삼성물산(주)) Period : 2000 ~ 2008 Summary : Caisson, dredging, wharf structure, reclamation, quay wall
February, 2000

Incheon gas storage terminal [인천정유소 해상출하부두 건설공사]

Project name : Incheon gas storage terminal-Loading platform (인천정유소 해상출하부두 건설공사) Project owner : GS Caltex / GS E&C (GS칼텍스 / GS건설(주)) Period : 2000.FEB ~ 2000.OCT Summary : Jacket Installation 12.6 * 12.6 * 26.0 : 2 Jackets Jacket Pile 1,016 : 124pcs
March, 1999

“J” project for Jinhae naval base [진해해군본부 J시설건설공사]

Project name : “J” project for Jinhae naval base (진해해군본부 J시설건설공사) Project owner : Korea Navy Force / Samsung Heavy Industries (SHI) (해군본부 / 삼성중공업(주)) Period : 1999.MAR ~ 2000.DEC Summary : Caissons 1300~1600ton : 38units
February, 1999

Bukok combined power plant [부곡 복합화력발전소 건설공사]

Project name : Bukok combined power plant (부곡 복합화력발전소 건설공사) Project owner : LG Energy / GS E&C (LG에너지 / GS건설(주)) Period : 1999.FEB ~ 1999.JUN Summary : Grab Dredging Soil : 205,731m3 Rock : 50,000m3
December, 1998

Busan metro 2-208 [부산지하철 2호선 208공구 토 공사]

Project name : Busan metro 2-208 (부산지하철 2호선 208공구 토공사) Project owner : Busan Transportation Corporation (BTC) / DAELIM E&C (부산교통공사 / 대림산업(주)) Period : 1998.DEC ~ 2003.JUN Summary : Site development for metro infrastructure
July, 1998

Busan LG metro city apartment [부산 LG 메트로시티 토공사]

Project name : Busan LG metro city apartment (부산 LG 메트로시티공사중 토공사 및 흙막이공사) Project owner : GS E&C (GS건설(주)) Period : 1998.JUL ~ 2004.OCT Summary : Site development for apartment complex