parallax background
May, 2000

Ulsan new port [울산 신항 방파제 공사]

Project name : Ulsan new port (울산 신항 방파제 공사) Project owner : Ministry of Maritime Affairs and Fisheries (South Korea, MOMAF) / Samsung E&C (울산해양수산청 / 삼성물산(주)) Period : 2000 ~ 2008 Summary : Caisson, dredging, wharf structure, reclamation, quay wall
February, 1999

Bukok combined power plant [부곡 복합화력발전소 건설공사]

Project name : Bukok combined power plant (부곡 복합화력발전소 건설공사) Project owner : LG Energy / GS E&C (LG에너지 / GS건설(주)) Period : 1999.FEB ~ 1999.JUN Summary : Grab Dredging Soil : 205,731m3 Rock : 50,000m3
February, 1992

Geoje Samsung shipyard project [삼성 거제 조선소 항만공사]

Project name : Geoje Samsung shipyard project (삼성 거제 조선소 항만공사) Project owner : Samsung Heavy Industries (SHI) (삼성중공업(주)) Period : 1992.FEB ~ 2012 Summary : Caisson, dredging, pile driving, reclamation, quay wall